Task Targeted Completion
Convene work group, review proposal, expand implementation plan 03-08-07
Provide information to HR work group for CSR recruitment 03-23-07
Network/Provider Services Manager hired and on board 04-20-07
Customer Services Representatives hired 05-15-07
Training of all CSR staff completed 06-21-07
Live practice week 06-29-07
Install and test 1-800 numbers 05-16-07
Write and get necessary approvals for call routing, policies and procedures, and auto attendant scripts 06-07-07
Finalize call routing, auto attendant scripts 06-14-07
Test all call routing 06-21-07
Participate in Readiness Review Date TBD by SRS
Determine reports required from Avaya call management system 04/20/07
Program system for required reports; test programmed reports 06/01/07
Provider Relations
Task Targeted Completion
Identify potential network providers 01-07-07
Convene work group, review proposal, expand implementation plan 03-02-07
Finalize provider communication materials (including cover letter, FAQ’s, application packet, rates and contracts 03-07-07
Mail communication materials (including credentialing and contracting materials) and post FAQ’s to web-site 03-10-07
Track returned applications through credentialing and contracting All contract period
Provide telephonic support through National Provider Service Line (included enhanced hours) and establish on-site support for Kansas providers having difficulty completing applications 03-10-07
Develop training materials and schedule provider forums (both web-based and face-to-face) 4-01-07 – 07-01-07 (and ongoing as needed)
Assess network completeness and determine additional action steps if necessary to assure network adequacy for go-live 04-16-07 (and monthly through implementation
Provider Relations
Task Targeted Completion
Meet with SRS/AAPS to review provider handbook samples and determine format/content 04-15-07
Present provider handbook draft to SRS and/or provider representatives for review 05-01-07
Post handbook on Kansas Web site; print copies for distribution upon request1 05-01-07
Participate in Readiness Review Date TBD by SRS
In collaboration with SRS and RADACs, determine number of orientation meetings to be conducted and locations for each; book locations 04-17-07
Prepare and distribute announcements about orientation meetings to providers, future members, and other interested parties (generally orientation for members and providers are held on the same day and location with the morning focusing on one group the afternoon on the other. However, anyone is free to attend either or both orientation program) 04-17-07 – 07-01-07 (and ongoing as needed)
In collaboration with SRS, provider and client representatives, finalize agenda and presenters 05-15-07
Conduct orientation forums in multiple locations across Kansas 06-15-07
Load provider files into management information system 04-01-07 and throughout contract period)
Schedule and conduct additional orientation sessions during first contract year 06-30-08
Conduct provider forums at least twice annually 07-08
Clinical / Quality Assurance
Task Targeted Completion
Convene work group, review proposal, expand implementation plan 03-08-07
Provide information to HR work group for recruitment of staff for Clinical Dept 03-23-07
Clinical Director hired and on board 04-23-07
Intensive Care Managers hired and on board 05-15-07
Utilization Managers hired and on board 05-15-07
Clinical / Quality Assurance
Task Targeted Completion
Regional Representatives hired and on board 05-18-07
Training of all staff in Clinical Department completed 06-22-07
Live testing week 06-29-07
Participate in Readiness Review Date TBD by SRS
Review proposed work flows with SRS and representatives of RADACs 03-23-07
Develop policies and procedures based on proposed work flows, including:
• interface/information transfer between KCPC and CareConnect;
• care coordination with MCOs and community mental health centers; mixed services protocols;
• medical necessity criteria, level of care guidelines, treatment-based treatment guidelines;
• authorization letter templates; and
• clinical management reports, internal and external
05-15-07
Customize clinical training for clinicians and SA-PIHP providers 05-15-07
Complete initial memoranda of understanding with health plan, community mental health centers and other affiliated delivery systems that serve a high proportion of SA-PIHP clients 06-15-07
Provide training to Northeast Service Center night staff and other service centers designated as emergency back-up 06-20-07
Complete formal Utilization Management Plan for SA-PIHP 08-31-07
Interview candidates for Medical Director consultant; present recommended candidate to SRS 05-01-07
Training for selected consultant at other PSD Service Center and on-site in Kansas 06-15-07
Identify SA-qualified Peer Advisors from interview pool and from VO contract; provide orientation to SA-PIHP 06-15-07
(PE&O/Training Director) Implement outreach and communications efforts focusing originally on disseminating information about SA PIHP and 1-800 number 05-31-07
Create two-sided one-page program information sheet for distribution at orientation meetings and other venues; get approval from SRS and client/family representatives 04-16-07
Update one-pager At least monthly during implementation
Identify SRS staff and SA-PIHP clients/families to review drafts of Member Handbook 04-30-07
Clinical / Quality Assurance
Task Targeted Completion
Provide initial Member Handbook for posting on VO-KS Web site2 06-01-07
With support of SRS, review and modify Member Rights statements, policies and procedures currently used by RADACs 05-01-07
Finalize statement of Member Rights for SA-PIHP 05-15-07
With support of SRS (and KHPA), clarify grievance and appeal process for both Medicaid and non-Medicaid SA-PIHP members 04-06-07
Adapt policies and procedures to full compliance with Kansas regulations 04-20-07
Submit policies for review and approval by SRS 05-15-07
Program automated notices of action letters and other notifications for providers and clients to reflect approved policies 05-31-07
Design training for staff on grievances and appeals; incorporate into orientation as well as ongoing training modules 06-01-07
Adapt CareConnect complaint/grievance/appeal tracking module to support KS SA-PIHP processes 06-18-07
Recruit and hire QM Director; QM Director on board 04-27-07
Grievance/Appeal Specialist, PE&O/Training Specialist on board 05-18-17
Review proposed QM committee structure with SRS; negotiate final structure 04-16-07
Recruit members for committees 05-18-07
Submit initial QM plan3 10-01-07
Convene Clinical Performance Committee to focus on policies and procedures and provider profiling 04-08-07
Finalize Year #2 QM Plan for review by SRS/AAPS 08-31-08
Identify reports required by SRS and required internal reports 05-23-07
Submit recommended formats for SRS reports for approval 05-31-07
Complete programming for reports 06-22-07
Verify report accuracy Ongoing
Complete grid of contract deliverables Ongoing
Document delivery of contract deliverables Ongoing
Regular review of contract deliverable grid/ generate report Oct & ongoing
Clinical/Quality Assurance
Task Targeted Completion
Create training agenda for VO-KS staff and implement, including ttraining on cultural competency Oct & ongoing
Conduct member and provider satisfaction surveys TBD
Plan for and conduct Substance Abuse Summit 05-08

 

1 In many new programs, because policies and procedures are updated frequently in the early months of the contract period, printed copies of the Member Handbook are not made available until 90 days after go-live; the Handbook and revisions are available continuously on the website
2 In many new programs, because policies and procedures are updated frequently in the early months of the contract period, printed copies of the Member Handbook are not made available until 90 days after go-live; the Handbook and revisions are available continuously on the website, and one-page summaries or other handouts are made available to explain the most important program features including the 1-800 numbers, Member Rights, grievances and appeals, services and how to access them.
3 Many QM activities cannot be initiated until a sufficient body of data is collected to assure that reports are both reliable and valid. Therefore in most programs, finalization of the QM plan is delayed to provide state staff and other stakeholders the opportunity to participate in its development

 

>
Facility Set-Up
Task Targeted Completion
Review proposal and contract for additional/changed requirements 03-08-07
Identify available appropriate properties; review and select 03-23-07
Identify and contract for temporary space/equipment/furnishings 03-30-07
Finalize build-out requirements and office configuration 04-16-07
Finalize and sign lease 04-23-07
Sign contract for build-out if necessary; begin build-out 04-23-07
Approve completion of build-out; move into permanent location 06-01-07
Verify office equipment needs; complete order 05-01-07
Install office equipment and furnishings 06-08-07
Establish office services including UPS and FedEx for temporary and permanent locations, post office box(es) 04-03-07
Determine supply needs; order supplies for temporary and permanent space 06-01-07
Information Technology
Task Targeted Completion
Included in dedicated IT implementation submitted in response to Section 5.7.16 of the proposal  
Claims, Eligibility and System Configuration
Task Targeted Completion
Convene work groups, review proposal, expand implementation plan 03-08-07
Request team members from SRS, KHPA, EDS and other agencies with whom interfaces will be established 03-09-07
Clarify processes required to provide to SRS information needed to support reimbursement of block-grant funded services 03-16-07
Receive list of approved services by funding stream and other information related to benefit design; load into BenefitConnect to support accurate claims payment, clinical and customer service 05-16-07
Identify all global configuration information critical to ensuring that all subsystems are appropriately linked within the system 04-16-07
Configure Connections Administrative System benefit designs for 04-23-07
Claims, Eligibility and System Configuration
Task Targeted Completion
each funding stream  
Identify format for Title XIX eligibility feeds 03-16-07
Program eligibility load program; configure eligibility client configuration and load sample eligibility tape 05-16-07
Claims model office testing to validate all sub-systems are fully and appropriately configured 05-16-07
Offer providers opportunity to submit trial claims as training/compatibility assessment 06-01-07
Provide telephonic and on-site support for providers Ongoing
Participate in Readiness Review Date TBD by SRS
Finance
Task Targeted Completion
Convene work group, review proposal, expand implementation plan 03-08-07
Request team members from SRS and KHPA with whom interface will be established 03-09-07
Provide information to HR work group for recruitment of CFO 03-23-07
CFO hired and on board 05-22-07
Determine any unique payroll requirements; set up VO-KS payroll 03-08-07
In collaboration with SRS, establish financial reporting requirements and implement any required changes to existing VO policies and procedures 04-13-07
In collaboration with SRS and KHPA, establish billing/ reimbursement process including wire transfer service 05-15-07
Set up internal general ledger accounts within ValueOptions for VOKS 05-15-07
Identify any special internal reporting needs and implement needed changes 06-01-07
Participate in Readiness Review Date TBD by SRS
Prepare required audit information for SRS TBD
Human Resources/Community Partnerships
Task Targeted Completion
Convene work group, review proposal, expand implementation plan 03-08-07
Gather job descriptions from all work groups; initiate recruitment efforts, including posting internal notices and advertising in selected media 03-23-07
Coordinate distribution of incoming resumes and scheduling of 03-23-07
interviews  
Support Implementation Team, CEO and incoming new staff to complete processes required for filling VO-KS positions including background checks as necessary Ongoing
Set up personnel files for all VO-KS positions 04-06-07
Establish internal P&Ps for personnel transactions that are compliant with VO and Kansas requirements 04-30-07
Recruit and hire Executive Assistant/HR Director; on board 05-18-07
Orientation and training complete 05-31-07
Post all required employee information posters relating to workman’s compensation, EEOC, VO Ethics Hotline 06-01-07
Participate in Readiness Review Date TBD by SRS
Implementation Team/Service Center Leadership
Task Targeted Completion
Meet weekly with SRS/AAPS/KHPA staff for implementation updates Throughout Imp period
Establish regular contract meetings at least monthly with SRS/AAPS/KHPA and/or other designated contract managers 08-07-07
Become active participant in existing meetings, such as Consortium meetings, at direction of SRS/AAPS or invitation of other groups Ongoing
Join SRS effort to support treatment for co-occurring disorders Ongoing
Complete letters of agreement with all major referral agencies outlining communication protocols Ongoing

 

Medicaid Training Menu Image Go to information about Prepaid Ambulatory Health Plan! Go to Medicaid Training home page! Go to informaition about Prepaid Inpatient Health Plan!!! Go to information about Psychiatric Residential Treatment Facilities!!! Go to information about Youth Residential Services - Preferred Futures